PJM Interconnection has released the results of its 2028/2029 Base Residual Auction (BRA), with the market clearing at the FERC-approved price cap of $325/MW-day across the PJM footprint.
While the auction cleared at the cap for the second consecutive year, the clearing price represents a 2.5% decrease from the 2027/2028 auction price of $333.44/MW-day. The reduction reflects annual adjustments to the price cap calculation, which is based on the accredited capacity of PJM’s reference resource.
Key Takeaways
- Capacity Shortfall Continues: The auction procured 138,318 MW of unforced capacity, leaving the region 6,831 MW short of PJM’s reliability requirement. This shortfall is slightly larger than the approximately 6,500 MW shortfall recorded in the previous auction.
- Reliability Maintained, but With Tighter Reserves: A capacity shortfall does not necessarily indicate that PJM will be unable to meet demand during peak conditions. However, it does mean the grid will operate with slimmer reserve margins and elevated reliability risk. PJM’s reserve margin for the 2028/2029 delivery year is projected at 14.7%, compared to 14.9% in the prior auction.
- Uniform Pricing Across PJM: Unlike the 2026/2027 and 2027/2028 auctions, this year’s auction did not result in zonal pricing differences. As a result, the capacity clearing price is consistent across all PJM utility service territories.
- Looking Ahead: The next Base Residual Auction for the 2029/2030 delivery year is currently scheduled for December 2026. Similar to recent auctions, the market will operate within a pre-approved price collar consisting of a price cap and price floor.
The results continue to underscore the growing challenge of balancing increasing electricity demand with the pace of new generation development and grid expansion. PJM has indicated that it will continue pursuing initiatives designed to accelerate new resource development, improve interconnection timelines, and address near-term reliability needs.
For additional information, visit PJM’s announcement: PJM Capacity Auction Procures 138,318 MW of Generation Resources as Work Continues To Address Growing Electricity Demand
A detailed auction report will also be published on PJM’s Capacity Market webpage.
Please contact your EnerConnex representative with any questions about how these results may affect your energy strategy or procurement planning.